Installing a basement support post is a common way to correct a sagging floor joist, eliminate bounce in a floor above, or provide extra reinforcement after a wall has been removed. This guide covers the process for a standard adjustable steel jack post (also called a lally column or screw jack). The job requires basic carpentry tools and a careful eye for level and plumb. Before you begin, confirm that the footing beneath the concrete floor is thick enough to support the load; if you are unsure, consult a structural engineer. This is not a job for a temporary jack stand—use a permanent, load-rated post designed for structural support.

What You’ll Need

  • Adjustable steel support post (sized to fit your basement ceiling height)
  • Temporary support jacks or screw jacks (at least two, rated for the load)
  • Solid wood blocking or a steel bearing plate (if the post does not sit directly on concrete)
  • Circular saw or reciprocating saw (for cutting wood blocking)
  • Hammer and pry bar
  • Level (a 4-foot level is ideal)
  • Tape measure
  • Pencil or chalk line
  • Safety glasses and work gloves
  • Shims (steel or composite, not wood, for final adjustments)
  • Optional: concrete drill and masonry anchors if you need to secure the base plate

Step-by-Step

  1. Identify the exact location. Mark the center of the sagging joist or the point where the floor above feels bouncy. The post must sit directly under a joist, not between joists. If the joist runs parallel to where you need support, you will need to install a beam (a doubled joist or steel beam) across the span—this guide assumes the post lands under a single joist.
  2. Check the footing. The concrete floor must be at least a few inches thick and free of cracks at the post location. If you have a sump pit, drain, or old pipe nearby, move the post away from it. If the floor is thin or suspect, you may need to break out a section and pour a proper footing—this is a job for a professional.
  3. Install temporary supports. Place two or more screw jacks on either side of the final post location, a couple of feet away, directly under the same joist or under a temporary beam (a long 2×6 or 4×4) that spans several joists. Raise each jack slowly and evenly, just enough to take the weight off the floor. Do not lift the floor more than a fraction of an inch—you want to stop the sag, not raise the floor.
  4. Measure for the post height. With the temporary jacks holding the load, measure from the bottom of the joist to the top of the concrete floor at the post location. Subtract about an inch from this measurement to allow for the adjustable screw mechanism and shims. Most adjustable posts have a range of a few inches; if your measurement falls outside that range, get a different length post.
  5. Prepare the base. Clean the concrete floor of debris and dust. If the floor is uneven, use a steel bearing plate or a solid wood block (treated lumber or pressure-treated plywood) to create a flat, level surface. The base plate of the post must sit fully flat on the floor. Do not use a single small shim under the base—use a full-size plate or a solid block that spans the entire base.
  6. Set the post in place. Position the post vertically under the joist. The top plate of the post should be centered on the joist. If the joist is not perfectly flat where the post meets it, you may need to add a steel bearing plate or a piece of plywood to distribute the load across the full width of the joist. Never let the post bear on just the edge of the joist.
  7. Extend the post to the joist. Turn the adjustment screw (usually a threaded rod or a screw jack mechanism) to raise the post until the top plate just touches the joist. Do not force it yet. Check that the post is plumb (perfectly vertical) using a level on two adjacent sides. Adjust the base or shim under the base if needed to correct plumb.
  8. Tighten to bear the load. Slowly turn the adjustment screw to raise the post by a quarter turn at a time. You want the post to take a firm, solid load from the joist, but you should not be actively lifting the floor. A good test: try to turn the screw by hand; if it becomes very hard to turn, you have reached the proper load. If you hear creaking or see the floor rise, back off slightly.
  9. Remove the temporary jacks. Once the post is snug and plumb, lower the temporary jacks one at a time, a quarter turn each, alternating between them. Watch the post and the joist for any movement. If the post settles or the floor drops, re-tighten the post and re-check the jacks.
  10. Secure the post (optional but recommended). Most adjustable posts have pre-drilled holes in the base plate. Use masonry anchors and a concrete drill to secure the base to the floor. This prevents the post from shifting during a minor earthquake or if the floor vibrates. For the top, you can screw a small metal angle bracket into the joist to keep the post from tipping, but do not rely on screws to carry the load.
  11. Final check. Re-check plumb with the level. Confirm that the post is bearing fully on the joist and the floor. Walk on the floor above—it should feel noticeably more solid. If there is any gap between the post top and the joist, use steel shims (never wood) to fill it, then tighten the screw a final half turn.

Common Mistakes

  • Using a post that is too short or too long. A post that is too short cannot be extended enough to bear the load; a post that is too long will not fit under the joist. Always measure twice and buy the correct size range.
  • Placing the post between joists. The post must be directly under a joist. If you cannot see the joists (finished ceiling), use a stud finder or drill a small pilot hole to locate them.
  • Over-lifting the floor. Raising the floor too much can crack the ceiling above, pull nails from drywall, or damage plumbing. You are correcting a sag, not jacking up a car.
  • Ignoring the footing. A post on a thin or cracked concrete slab will sink over time. If you have any doubt about the footing, get a professional opinion before you install.
  • Using wood shims. Wood compresses and rots over time. Use steel or composite shims for any final adjustment.
  • Not checking plumb. A post that leans even slightly can buckle under load. Check plumb in two directions before you tighten.

Tips

  • Work with a helper. Raising and lowering the temporary jacks is much easier with two people—one to turn the jack, one to watch the joist and the post.
  • Use a laser level or a straight 2×4 to check for a straight line across the joists before you start. This tells you how much sag you are correcting.
  • If the floor above is finished, place a small piece of cardboard or a cloth under the temporary jacks to avoid marking the floor.
  • Consider adding a second post if the span is very long. A single post in the middle of a long span may not be enough; a structural engineer can tell you the correct number and spacing.
  • Paint the post with a rust-inhibiting primer if it will be in a damp basement. Most steel posts come with a coat of paint, but scratches can rust.
  • Keep the post adjustment screw accessible. Do not build a wall or closet right up against it, because you may need to re-tighten it years later.

Troubleshooting

  • The post will not reach the joist. If the post is fully extended but still a fraction of an inch short, you can add a steel bearing plate or a piece of solid wood (at least an inch thick) on top of the post. Do not use multiple thin shims—they can slip. If you are more than an inch short, you have the wrong post length.
  • The floor still bounces after installation. This usually means the post is not bearing enough load. Re-tighten the screw by a half turn and check again. If it still bounces, you may need a second post or a larger beam.
  • The post is not plumb. Loosen the screw, adjust the base plate with shims, and re-tighten. If the concrete floor is sloped, you may need to grind it flat or use a thicker base plate.
  • You hear creaking or popping after installation. This is often the joist settling onto the post. Wait a day, then re-check the screw tension. If the creaking continues, check that the post is not rubbing against any framing or pipes.
  • The post base is not flat on the floor. If the concrete has a small bump or depression, use a grinder or a chisel to flatten it. Never try to compensate with a shim under just one corner of the base.
  • You accidentally lifted the floor too much. If you see cracks in the ceiling or the floor above feels raised, back off the post screw by a half turn, then re-check the temporary jacks. You may need to lower the jacks slightly to let the floor settle back down.

Frequently Asked Questions

Q: Can I install a support post myself, or do I need a professional?
A: A homeowner with basic tools and a good understanding of level and plumb can do this job. However, if the sag is severe, if there are multiple joists involved, or if you are unsure about the footing, hire a structural engineer to assess the situation first.

Q: How do I know what size post to buy?
A: Measure the distance from the concrete floor to the bottom of the joist at the installation point. Then subtract about an inch for the adjustment screw. Buy a post whose adjustable range covers that measurement. Most hardware stores sell posts in a few standard height ranges.

Q: Do I need a building permit?
A: In many areas, adding a structural support post requires a permit because it changes the load path of the building. Check with your local building department before you start. Even if a permit is not required, it is a good idea to have the work inspected.

Q: Can I use a car jack or a bottle jack as a permanent post?
A: No. Car jacks are not designed for continuous static loads and can fail suddenly. You must use a post that is specifically rated for structural support, such as an adjustable steel jack post with a load rating stamped on it.

Q: What if my basement ceiling is finished (drywall)?
A: You will need to cut a hole in the drywall to access the joist. Cut the hole slightly larger than the post base plate, install the post, then patch the drywall around the post. Be careful not to cut any electrical wires or plumbing—turn off power to the area if you are unsure.

Q: How much weight can a typical basement support post hold?
A: A standard adjustable steel post can support a significant load—often several tons—but the exact rating depends on the post diameter and wall thickness. Always check the manufacturer’s label. The post is only as strong as its footing and the connection to the joist, so those must be sound.